The objective of the government
The objective of the government
The objective of the government to resolve the energy crisis in the next two years with the goal of producing a thousand 450 megawatts of electricity is forwarded.
The government of Nepal Electricity Authority, its subsidiary company of Minister and private sector construction project promoters are urged to complete as soon as the goal is forwarded.
Authority is constructing the 32 MW project Chameliya and the project was completed the next deadline is stated. 14 MW capacity of the project.
A similar project is also enhanced by subsidiary companies to facilitate faster completion will be required. It is the major Upper Tamakoshi Hydropower Project. The project capacity is 456 MW. Upcoming mansiradekhi dam and other infrastructure work will be carried forward. India have been affected by the earthquake and undeclared sanctions, due to the construction of the project has already begun.
Similarly, Chilime Hydro Power Project by subsidiary companies Sanjen respectively, the upper Sanjen, construct the project will be the construction of speed.
Energy Minister Janardan Sharma, NEA's another important project being the construction of Upper Trishuli three A delay would soon end, and for its initiative has been.
He authority of its subsidiary companies and 850 MW hydro power project, 400 MW of solar private investors, a total of 200 MW jaivikalagayata sources thousand 450 megawatts of electricity will be added to the internal grid, said.
Similar Dhalkebar-Muzaffarpur transmission line will add 600 MW of electricity has been imported earlier agreement. Dhalkebar Chinese contractor substation construction work is moving ahead.
Dhalkebar work two siphtma
Energy Minister Sharma Dhalkebar speed substation construction process, he said. He said, "Recently two siphtma daily substation is being built. Chinese contractor is operating daily 300 more workers. "
Substation is aimed to complete the construction of the end of the next November. After completion of the substation will be easier to import electricity from India. 220 kV substation capacity of more electricity will be imported and the government to resolve the energy crisis in the country is the target.
Similar Dhalkebar-Khimti transmission line construction has reached its final stage. The project is ongoing, effective monitoring of vital construction project that will be completed in due time, the NEA Director broadcasting major kanhaiyalal MANANDHAR says.
Leakage Control Campaign continues
Similarly, leakage control and effectively implement energy efficiency programs, the government is planning. Authority Executive Director navaniyuukta Kulman Ghishing leakage as major action plan to move forward the agenda of the public.
The flow of electricity to the national transmission line will be 25 percent electricity leakage NEA. Only able to control the leakage of 250 megawatts of electricity could be prevented NEA.
NEA dues of Rs ten billion is the same. Dues Minister and leakage control and the campaign as a campaign ahead is to continue to keep the ministry said.
Large capacity transmission line will be
The government is currently in practice instead of the small and medium capacity transmission line 765 KV 400 kebhidekhi construction of major transmission lines as a campaign is to move ahead. The Authority is currently only 11 kebhidekhi 400 KV transmission line is built.
A couple of years more than ten thousand MW of electricity will be produced due to the need of a large capacity transmission highway Dinesh Ghimire, joint secretary at the Ministry of Energy. According to the ability of the river, the north-south high-voltage transmission line to start the construction work and the mid-hills Highway certain high voltage transmission line will be built even if the goal of the government is Ghimire, Joint Secretary.